Number: 2017-06
Bid Date has Changed Now Bids are Due: July 19, 2017 -5:00PM EST
Location: Graceland Park/O’Donnell Heights Elementary/Middle School No. 240: 6300 O’Donnell St. Baltimore, MD 21224 Map »
Holabird Elem/Middle School No. 229: 1500 Imla Street, Baltimore, MD 21224 Map »
Job Walk: June 14, 2017 – 10:00AM EDT start at Graceland Park/O’Donnell Heights Elementary/Middle School No. 240
Pre-Bid RFIs Due: July 5, 2017 – 5:00PM EST
Expected Start (New School): September 4, 2017
Expected Finish (New School): June 30, 2019
School Demo: Aug 2019 – Dec 2019
Final Sitework: Dec 2019 – June 2020
Architect: Grimm & Parker Architects
Description: This Bid is for the demolition and replacement of TWO (2) schools:
1) Graceland Park – O’Donnell Heights Elem/Middle School No. 240
2) Holabird Elem/Middle School No. 229
Both new schools will be 89,400 SF 2-story, K-8 schools, and will be built simultaneously. All major trades are involved including: hazmat abatement, demolition, sitework, concrete, masonry, steel, millwork, roofing, storefront, finishes, specialties, elevator, sprinkler, mechanical, and electrical.
Although drawings are very similar it is the trade contractors responsibility to determine scope of each project and bid accordingly.
THERE IS A JOB SITE WALK-THRU ON WED JUNE 14 AT 10:00 AM, STARTING AT GRACELAND AND THEN TO HOLABIRD (SEE ADDENDUM 3).
NOTE – FOR BOTH BUILDINGS: wage rates, unit prices, and alternates apply.
MBE REQUIREMENTS: MDOT Total goal – 32%, with African-American (7%) and Asian (4%) sub-goals.
This project is also available for public bidding via the Cam Construction Public Plan Room.
Project Documents
Civil & Landscape – Graceland Bid Set-Drawings
Civil & Landscape – Holabird Bid Set Drawings
Architectural & Structural – Graceland Bid Set-Drawings
Architectural & Structural – Holabird Bid Set Drawings
Food Service – Graceland Bid Set-Drawings
Food Service – Holabird Bid Set Drawings
MEP – Graceland Bid Set-Drawings
MEP – Holabird Bid Set Drawings
Graceland Bid Specs Vol 1
Holabird Bid Specs Vol 1
Graceland Bid Specs Vol 2
Holabird Bid Specs Vol 2
Asbestos Management Plan for Graceland Park 240
Asbestos Management Plan for Holabird EMS 229
Addendum 1 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 2 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 3 to IFB17073 Graceland EMS240 and Holabird EMS229
Prevailing Wage Rates-Graceland Park #240
Prevailing Wage Rates-Holabird EMS #229
Bidding Data, General Conditions and Wage Scale for Graceland EMS240 and Holabird EMS229
Bid Form-MBE and Bid Data-Graceland EMS240 and Holabird EMS229
Addendum 4 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 5 to IFB17073 Graceland EMS240 and Holabird EMS229 Addendum and Drawings
Addendum 5 to IFB17073 Graceland EMS240 and Holabird EMS229 NEW Asbestos Management Plan for Graceland Park 240_1c
Addendum 5 to IFB17073 Graceland EMS240 and Holabird EMS229 NEW Asbestos Management Plan for Holabird EMS 229_1c
Addendum 6 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 7 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 8 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 9 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 10 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 11 to IFB17073 Graceland EMS240 and Holabird EMS229
Addendum 12 to IFB17073 Graceland EMS240 and Holabird EMS229