Abingdon Volunteer Fire Department

The Abingdon Fire Station is a three-story masonry, load-bearing structure with grade access at both the first and second level. This structure required extensive site work due to the extremely sloping and wooded site. The upper level floors of the building are pre-cast concrete plank with concrete topping, and the roof structure consists of wood trusses with asphalt shingles.

The building has an apparatus bay that contains 10 truck areas serviced by electronically operated overhead doors. An administration area, computer center, control room, and living quarters are all incorporated in the three-story building. The fire station also has a large assembly room with a full service commercial kitchen that is housed on the lower level.

Abingdon Elementary School

This project involved two additions as well as extensive renovations to the existing Abingdon Elementary School. The east addition was approximately 26,000 square feet and included classrooms, multi-purpose areas, special education labs. The west addition was approximately 7,000 square feet and included special education, speech therapy, student counseling areas as well as a main vestibule entrance. Renovations included improvements to the kitchen, receiving line, cafeteria and dining areas.

The construction was broken down into three phases. Extreme caution was maintained throughout construction since the school was occupied. Temporary partitions and egress protection had to maintained through the existing main entry as well as through the food service facility during the term of construction.

Obviously, mechanical electrical and other utilities had to be maintained during the occupancy of the building.

In addition, the project also included improvements to the existing bus loops and the addition of a parking lot. The project was successfully completed and the additions were seamlessly blended with the exiting structure.

“We are so pleased with the results. Your perseverance even helped to complete the project ahead of schedule. Our students, teachers and community members are very appreciative of all of your hard work and expertise. We will get to enjoy the fruits of your labor for decades to come.”

Ms. Carol Strine
Assistant Principal Abingdon Elementary

Morgan State University – New Communications Center

This 82,500 square foot, three story facility includes a partial basement with an exterior structure designed to incorporate three different construction materials – brick fascia at the lower floor and foundation, transitioning to metal panels and the aluminum window wall system at the upper floors. Particular attention was paid to the transitions between the separate façade systems such that water infiltration could be eliminated. The metal wall panels are backed by structural studs and Dens-Glas sheathing system. A few of the challenges on the exterior skin were the coordination and installation of the fin wall system, the storefront and canopy and the building structure. Coordination and installation of the sun shade and brackets also required expert installation in that the system is installed behind the metal wall panels. The building has been designed with composite systems, eliminated bar joists, speeding erection and making the project less sensitive to weather delays.

Also included in this contract was the new pedestrian footbridge connecting Bannecker Hall to the new Communications Center. The heavily wooded, steeply sloped site required great care on CAM’s part to minimize impact to the environment while still completing the connection between the two structures and the campus itself. At its highest point this more than 400 foot long bridge is 80 feet above the valley below with two girder trusses spanning 125 feet.

The lower level of the new Communications Center was designed to house the future telecom data infrastructure for the entire campus. The floors above include lecture halls, classrooms, a production studio, as well as the campus radio station. All of these rooms included critical consideration for sound attenuation systems for the mechanical equipment surrounding these spaces. CAM’s project manager and field superintendent successfully coordinated the installation of a myriad of sound attenuation systems that permeated nearly every subcontractor on the project. The studios have sound absorption doors, walls, glass, and floor systems as are found in a professional studio environment. The classrooms, faculty offices and another graphic design studio are located on the second and third floors and each have their own set of special requirements.

Fifth District Volunteer Fire Station + Ten Oaks Ballroom

The project consisted of the construction of a new fire house that contained an 8,350-square foot engine bay, an 18,000-square foot support center, and a 12,500-square foot community hall. Construction is brick, with block back-up using shaped brick, hinged brick, and tile in-lays. Special features include a full-service kitchen and dining room for fire department, a dormitory, and a recreation area.